Automation of high-speed production lines
Project
Integration and installation of automatic robotic packaging machines into existing processes. Installation of an automatic raw material preparation robot, project management of the installations.
Solution
After testing the improved part in a virtual environment, tests are performed in -40 and then +80 C.°
Used technologies, tools
In the development and test phase, plastic parts were produced by machining, in the mass production phase by injection moulding. The aim of the projects was to replace the raw material used.
Design optimisation of braking system components
Project
An upgrade of the mechanical time switch by one of the world's largest brake system manufacturers. Redesign of plastic component design with changes in raw material and manufacturing processes.
Solution
After testing the improved part in a virtual environment, tests are performed in -40 and then +80 C.°
Used technologies, tools
In the development and test phase, the plastic parts were produced by machining (turning, milling, drilling) and in series production by injection moulding. The main objective of the project was to replace the raw material used.